· 7 min read
Planning an Office Fit-Out with Glass Partitions
How to plan glass partitions within an office fit-out: timing, coordination with other trades, building approvals and avoiding common pitfalls.

Bring glazing in early
Partition positions affect lighting, sprinklers, air conditioning, floor boxes and furniture. Involving a glazing specialist early avoids late redesign and site clashes.
Typical sequence
On many fit-outs, the sequence looks like this:
- Space planning and partition layout agreed.
- Site survey and system specification.
- Drawings approved and materials ordered.
- Ceilings, M&E first fix and flooring progressed.
- Partitions and doors installed.
- Manifestation, snagging and handover.
Building approvals
Many managed buildings require RAMS, landlord approval and agreed working hours. Allow time for these in the programme.
Bring the glazing contractor in early
Glass partitions interact with almost every other trade: ceilings, mechanical and electrical, flooring, furniture and IT. Involving the glazing contractor during design means head details, deflection allowances and door positions are coordinated before ceilings are installed, which avoids expensive rework later.
A typical sequence
On most fit-outs, the glazing work follows this order:
- Early design input and budget pricing from layout drawings.
- Site survey once the shell is clear and key services are known.
- Technical drawings and setting-out approval.
- Manufacture, which commonly takes several weeks depending on system and glass type.
- Installation after ceilings and before final flooring, carpet tiles and decoration where possible.
- Final glass cleaning, door adjustment and handover documentation.
Coordinating with landlords and building managers
Most London office buildings require approval for works. Expect to submit method statements, risk assessments and sometimes drawings to the building manager, and to agree delivery times, goods lift bookings and out-of-hours working. In multi-tenant buildings, noisy work such as drilling into the slab may be restricted to evenings or weekends. Our glazing contractor timelines guide sets out realistic lead times.
Budgeting sensibly
Partition cost is driven by linear metres of wall, glass specification, number of doors, acoustic targets and access. Building in a contingency for site conditions, such as uneven floors or unexpected services in the ceiling void, protects the programme. The office partitioning budget guide gives a breakdown of where money is typically spent.
Questions
Should glass partitions go in before or after the ceiling?
It depends on the design. Partitions that run to the slab are usually installed before the ceiling; partitions that stop at a suspended ceiling are installed afterwards against a pre-agreed head detail.
Who handles building control for glass partitions?
On most fit-outs, the main contractor or design team manages building control. The glazing contractor supplies product data, test evidence and compliance information for safety glass, manifestation and any fire-rated elements.
